Unforeseen circumstances may require changes to the Grant Contract or approved application. Always contact the JTS first — they advise on the procedure and documents needed before anything is submitted to the CA/IBFM.
The procedure depends on the scale of the change — from a simple notification to a formal addendum requiring EUD approval.
Coordinator notifies the CA/IBFM without delay — no prior approval needed.
Exceptional, substantial deviations from the approved application. Maximum grant amount can never increase.
Changes must never put the project's basic objectives or the grant award decision in question.
Requests lacking justification or supporting documentation will be rejected.
The maximum Grant amount referred to in the Special Conditions may never be increased.
All modification requests must be signed by the authorised representative(s).
Only after JTS consultation does the Coordinator submit officially to the CA/IBFM.
Last modification request ideally reaches the JTS ≥ 2 months before the project end date.
Core templates for minor amendments and for presenting the modified budget for any budget-related change.
Standard template used to formally request a major amendment, together with a revised Annex III budget.
Visual step-by-step summaries of the minor (2.8) and major (2.9) modification processes.